Q14 — Engineering Economics

Q14

#0000095089

14 / 155

The table presents four alternative water projects described by incremental costs and benefits. Which project should be selected?

Project Incremental Cost Incremental Benefit
A $43,670 $44,993
B $57,812 $59,354
C $49,616 $55,770
D $62,175 $66,421